Progress on Lausanne tramway

Switzerland's Federal Office of Transport has approved the second phase of the Lausanne tramway, clearing the way for a 3.1-kilometre northern extension from Renens to Villars-Sainte-Croix

Construction could start in 2027 and run for around four years, subject to any appeals.

The new stretch will add six stations, connect Renens station to the Villars-Sainte-Croix industrial zone in eleven minutes, and put the Lausanne-Flon terminus 26 minutes away.

The project is costed at CHF 290.5 million, with the canton covering 62%, the Confederation 25% and the four communes involved 8%.

The first phase, between Renens and Lausanne-Flon, is due to open at the end of this year

More from Bitesize News

  • Annecy mayor visits local school

    Antoine Armand, elected mayor of Annecy in March, has made his first back-to-school visit as head of the cross-border city, meeting pupils and teachers at Cran-Gevrier's Vernay school on Tuesday morning

  • Climate change affecting rainfall patterns

    Rain in Switzerland is falling less often but more heavily when it does, and the trend is likely to continue, according to MeteoSwiss

  • More security checks after Aarau shooting

    Every big public event is likely to face tighter security after the fatal Aarau festival shooting, according to former national security chief André Duvillard

  • Swiss Life job losses

    Zurich-based insurer Swiss Life will cut around 600 jobs by the end of 2028, with half of them in Switzerland

  • Crans Montana bar missed crucial checks

    The security officer for Chermignon has told Valais prosecutors that no proper inspection of the Constellation bar ever took place before it opened in December 2015

  • Fire cause revealed

    Authorities now believe a lithium battery may have triggered Friday's warehouse fire at the Thévenaz-Leduc recycling site in Ecublens, though the cause has not yet been formally confirmed

Download our app

  • Available on the App Store
  • Available on Google Play